SMART Material Control™ for District Utility Relocation and Construction
OnTraxSys Role:
Full lifecycle material control across 4 EPC contractors and multiple laydown yards.
OnTraxSys supported material control for the Customer’s utility relcation and new construction by handling oversight of $350M of electrical material including but not limited to overhead catenary hardware (arms, droppers, brackets, tensioners, conductor, pole line hardware, and major equipment).
Execution Highlights:
- >98.5% material availability rate at time of contractor need.
- <24-hour QA/QC and material discrepancy resolution for all shipments.
Measured Impact:
- Zero contractor downtime attributed to material unavailability across 18-month active construction window.
- Reduction of surplus material waste by >12% through reconciliation and redistribution to other projects.