OnTraxSys utility relocation and new construction material control.

SMART Material Control™ for District Utility Relocation and Construction

OnTraxSys Role:

Full lifecycle material control across 4 EPC contractors and multiple laydown yards.

OnTraxSys supported material control for the Customer’s utility relcation and new construction by handling oversight of $350M of electrical material including but not limited to overhead catenary hardware (arms, droppers, brackets, tensioners, conductor, pole line hardware, and major equipment).

Execution Highlights:

  • >98.5% material availability rate at time of contractor need.
  • <24-hour QA/QC and material discrepancy resolution for all shipments.

Measured Impact:

  • Zero contractor downtime attributed to material unavailability across 18-month active construction window.
  • Reduction of surplus material waste by >12% through reconciliation and redistribution to other projects.